Summary Job Schedule -- Kootenia Homes, Inc.
|
|
|
|
|
 |
| Friday 07/13/08 |
Contract Agreement |
Yes |
Friday 07/13/08 |
| Monday 07/16/08 |
Permits |
Yes |
Tuesday 07/31/08 |
| Wednesday 08/08/08 |
Excavation/Digging |
Yes |
Wednesday 08/08/08 |
| Thursday 08//08/08 |
Footings |
Yes |
Thursday 08//08/08 |
| Friday 08/03/08 |
Foundation/Concrete/Block |
Yes |
Thursday 08/09/08 |
| Friday 08/10/08 |
Structural Steel |
Yes |
Friday 08/10/08 |
| Friday 08/10/08 |
Waterproofing |
Yes |
Friday 08/10/08 |
| Monday 08/13/08 |
Deliver Garbage Container |
Yes |
Monday 08/13/08 |
| Monday 09/17/08 |
Roofing/Shingles |
Yes |
Friday 09/21/08 |
| Tuesday 09/18/08 |
Windows and Doors |
Yes |
Wednesday 09/19/08 |
| Thursday 09/20/08 |
Electrical Walk-through |
Yes |
Thursday 09/20/08 |
| Wednesday 10/03/08 |
Framing Inspection |
Yes |
Wednesday 10/03/08 |
| Wednesday 10/31/08 |
Cabinets and Vanities |
No |
Monday 11/08/08 |
| Tuesday 11/13/08 |
Painting Interior |
No |
Tuesday 11/27/08
|
| Friday 12/28/08 |
Adjust windows |
No |
Friday 12/28/08
|
| Monday 12/31/08 |
Mfg. Fireplace - Finish |
No |
Monday 12/31/08
|
| Monday 12/31/08 |
Customer Walk Through |
No |
Monday 12/31/08
|
| Wednesday 01/08/08 |
Punch List |
No |
Wednesday 01//08/08
|
| Thursday 01/03/08 |
Completion |
No |
Thursday 01/03/08 |
 |
*Please note that this not a complete Job Schedule. It has samples from the start, middle and end of the schedule.
Why is our Job Schedule so important? Customer Satisfaction.
|
|

|